The Double Oak section of the project includes the upgrade of approximately 2,550 feet of that same existing stretch of two-lane open-ditch section roadway to a two-lane urban street section, also with storm drainage system and sidewalk. Double Oak’s share of the construction is $2.3 million.

Because this is a joint project, the responsibilities for the project are divided. Flower Mound is responsible for contract administration. Changes of work within the Double Oak limits require Double Oak’s written approval.

Lane closures and traffic switches will be communicated through the town of Flower Mound website and on social media.